Sludge Digestion Calculations:

Oxygen requirement calculation for aerobic sludge digesters can be estimated based on information in the Metcalf & Eddy handbook. First, the mass of oxygen required per mass of sludge digested is based on the following stoichiometry:

The following overall reaction applies

C5H7NO2 + 7O2 Arrow 5CO2 + NO3 + 3H2 O + H

The weight ratio (O2 Ratio) for this overall reaction is 2:1  O2 / Biomass digested. This ratio applies for waste activated sludge from the activated sludge process.

Butler County Case

Primary sludge will have a lower ratio, which can be estimated from the BOD5 loading of the waste sludge from the primary clarifier. If primary sludge is introduced into the digester, the weight ratio can be estimated from its BOD5 loading and its percentage of the flow into the digester.

The typical solids loading to an aerobic digester is 1.5% to 3%, depending on the degree of thickening.

The handbook states that the reduction in Volatile Suspended Solids (VSS) by aerobic digestion is 40% to 50%. An experienced wastewater engineer and plant superintendent states that it is typically closer to 30%. Typical hydraulic retention times employed are as follows:

Waste Activated Sludge Only: 10-15 Days
Waste Activated Sludge from Plant without Primary Clarification: 12-18 Days
Primary + Waste Activated Sludge or Trickling Filter Sludge: 15-20 Days

The oxygen requirement for an aerobic digester can be estimated as follows:

  

If the digester is to be filled and aerated over several days, the hydraulic retention time (HRT) during the fill period can be counted as about half the effective time if the basin was full. For example, if the digester is to be filled/aerated over seven days, and then aerated for seven more days the effective total HRT will be about 10 days.

Effective HRT = (Fill Day)/2 + Full Days

__________________________________

Click to see more information about each application below:

1 Sewer Main Aeration 3 Activated Sludge Aeration 5 Post Aeration
2 Odor Control 4 Pure Oxygen Injection 6 Sludge Digestion
7 Ozone Disinfection

1-Sewer Main Aeration 2-Odor Control 3-Aeration 4-Pure Oxygen 5-Post Aeration 6-Sludge Digestion 7-Ozone for Disinfection


Look for The Mazzei® Design . . . Because It's What's Inside That Matters!

Click to Find Out More About Mazzei Injectors Technical Support Staff                           Same-Day Shipping                           High Quality Materials - PVDF, ECTFE, 316L Stainless Steel                           Continued Customer Support                           Experienced Engineers                           Patented Technology                           Quality Products                           Over 27 Years in Business
 

 

The Mazzei Look is a three-dimensional registered trademark.